Preparing a development equity funding schedule by project phase

A practical guide for sponsors to build a phase-by-phase equity funding schedule that shows lenders exactly when and how equity will be contributed, with a downloadable worksheet template.

Source: CodexTopic: Construction budget controls1063 wordsUpdated 2026-11-19

A practical guide for sponsors to build a phase-by-phase equity funding schedule that shows lenders exactly when and how equity will be contributed, with a downloadable worksheet template.

When you approach a lender for construction financing, one of the first questions they will ask is how your equity is structured and when it will be available. A well-prepared equity funding schedule by project phase demonstrates that you have thought through the financial demands of each stage and that your capital will be in place when needed. This guide explains how to prepare that schedule, what lenders look for, and how to avoid common pitfalls.

Why a phase-by-phase equity schedule matters

Lenders want to see that your equity is committed before their funds are disbursed. The OCC Commercial Real Estate Lending handbook states that a bank's policy should require equity be contributed before disbursements of the construction loan commence [1]. A phase-by-phase schedule shows that you have mapped your equity contributions to each stage of development. This is not just a formality: it directly affects how a lender views your project's risk. The source notes that deferring equity can increase completion risk [1].

What to include in your equity funding schedule

Your schedule should be a simple document that lists each project phase, the total cost for that phase, the amount of lender funding you expect, and the equity you will contribute. For each phase, identify the source of equity: cash, marketable securities, land purchased with cash, or initial costs paid up front such as architect and engineering fees and permits [1]. The schedule should also show the cumulative equity contributed to date and the remaining equity to be funded.

How to distinguish equity from non-equity items

A common mistake is including items that lenders do not count as equity. The OCC handbook is explicit: deferred developer's profit, unearned developer fees, incurred overhead expenses, or interest or other holding fees paid or accrued on contributed land do not contribute to the value of the project and are generally not considered equity [1]. When you prepare your schedule, you may need to separate these items for clarity. Show your cash equity and hard-cost contributions in one column, and list non-equity items separately so the lender can see you understand the distinction.

Structuring equity for phased developments

If your project has multiple phases, lenders typically finance each phase with separate loans or sublimits, with funding of subsequent phases dependent on the performance of the previous phase [1]. Your equity schedule should reflect this. For example, if Phase 1 includes common amenities like a clubhouse or infrastructure that benefits all phases, the lender may apply a portion of unit release prices to pay down the loan amount for those common improvements [1]. Your schedule should show how equity for common improvements is allocated and when it will be recovered from later phase proceeds.

The timing of equity contributions

Lenders generally require your equity to be invested before the first loan draw is funded [2]. Your schedule should show the timing of each equity contribution relative to the construction draw schedule. For example, if you plan to contribute equity at the start of each phase, state that clearly. If some equity is deferred to a later point in the development process, the lender will want assurance that this equity is and will remain available [1]. A practical approach is to show a timeline with key milestones: land closing, site work start, foundation, framing, dry-in, and so on, with equity amounts tied to each milestone.

How lenders test your equity commitment

Lenders evaluate your equity commitment by comparing loan-to-cost (LTC) alongside loan-to-value (LTV) [1]. Your equity schedule directly supports the LTC calculation. The lender will also analyze your financial condition to determine if you have sufficient financial capacity for project completion [1]. This means your schedule should be backed by evidence of available funds: bank statements, letters of credit, or commitment letters from equity partners. The schedule itself is a planning document, but the lender will ask for proof that the equity exists.

What to do if equity comes from multiple sources

If your equity comes from multiple partners or includes mezzanine debt or preferred equity, your schedule should show each source separately. Where the senior lender permits it, part of the equity can be replaced with mezzanine debt or preferred equity [2]. However, the senior lender's approval is required, and the terms of that subordinate financing will affect the overall risk picture. Your schedule should note which equity sources are subject to lender approval and which are unconditional.

Suggested worksheet: equity funding schedule by phase

To prepare your equity funding schedule, create a document with the following columns for each project phase: phase name, total phase cost, lender funding amount, sponsor equity amount, equity source, equity type (cash, land, pre-paid costs), timing of contribution, and cumulative equity to date. Below the phase-by-phase breakdown, add a summary row that shows total project cost, total lender funding, total sponsor equity, and the resulting LTC ratio. Also include a section listing non-equity items (deferred fees, overhead, interest reserves) that are part of the budget but not counted as equity. This worksheet is a suggested way to prepare information for your lender; it is not a mandatory form, and each lender may have its own requirements.

Common questions about equity funding schedules

How detailed should my equity schedule be?

Your schedule should be detailed enough to show the lender exactly when and how equity will be contributed for each phase of development. Include specific dollar amounts, sources, and timing tied to construction milestones. The lender will use this to assess whether your equity commitment is sufficient and timely.

Can I count the value of land I already own as equity?

The source lists land purchased with cash as an example of equity [1]. However, if you have a loan on the land, the lender may treat the land value differently. Check with your specific lender on how they treat land that was acquired with debt.

What if I cannot contribute all equity before the first draw?

Lenders generally require equity before the first draw [2]. If you need to defer some equity, you must demonstrate that the deferred equity is and will remain available [1]. Be prepared to explain why the deferral is necessary and how it reduces risk to the project.

Run the numbers on your deal

See how loan-to-cost and value at completion size a construction loan, how much equity is left to fund, and an estimated interest reserve.

Open the construction calculator

Talk through your financing

Working on a real property? Send us the deal and a financing advisor will review it and get back to you. It costs nothing to ask and does not commit you to anything.

Contact us

Requests are reviewed by Wraith Real Estate, a commercial real estate debt advisor (not a lender).

Sources

  1. OCC Commercial Real Estate Lending handbook
  2. Wraith construction loans