Reconciling a draw request with progress reported by the project team
A practical guide for sponsors preparing a construction draw request that aligns with the project team's progress reports, including a checklist to reconcile budget, inspection, and lien waiver documentation before submission.
A practical guide for sponsors preparing a construction draw request that aligns with the project team's progress reports, including a checklist to reconcile budget, inspection, and lien waiver documentation before submission.
This guide helps a commercial real estate sponsor prepare a draw request that matches the progress the project team reports on site. The goal is to hand the lender a package that answers the same questions the lender's own inspector will ask.
How a draw request and a progress report relate
A construction draw request is the sponsor's certification that work has been completed to a certain point and that the loan funds requested match that work. The project team's progress report—usually prepared by the general contractor or a third-party inspector—documents what is actually in place on site. The lender uses both to decide whether to release funds. [1] The OCC's handbook states that banks typically require inspection reports with each draw to verify that work is done according to specification and that the budget remains in balance with sufficient funds available to fund completion. [1]
The sponsor's job is to make sure the dollar amount on the draw request equals the percentage of work the inspector says is complete, less any retainage held back under the loan agreement. [2]
Preparing a draw reconciliation worksheet
A suggested way to prepare information is to create a single-page worksheet that compares three columns side by side: the line items from the approved budget, the percentage of completion reported by the project team for each line item, and the dollar amount requested for that line item. The worksheet should also show the retainage percentage required by the loan agreement and the net amount to be disbursed.
The worksheet should record the date of the inspection report that supports the percentages, the name and title of the person who signed the report, and a note about whether the inspector found any deficiencies. [1] The OCC's handbook describes inspection reports that typically state compliance with plans and specifications, support disbursements based on percentage complete, and state whether the project is progressing as anticipated. [1]
Identifying the budget categories that matter most
A construction budget usually groups costs into hard costs (labor, materials, subcontractor trades), soft costs (architecture, engineering, permits, legal), and financing costs (interest reserve, loan fees). The draw request should address each group separately because the lender treats them differently.
Hard costs are the primary focus of progress inspections. Soft costs are often front-loaded or incurred on a schedule that does not match physical construction. The interest reserve is drawn according to the loan agreement's formula, not according to site progress. [2]
Reconciling the timeline between a current rent roll and a trailing twelve month report
If the project is a renovation of an income-producing property, the draw request may need to reference operating data. A current rent roll is a snapshot of who is in place and what they owe this month. A trailing twelve month (T-12) report shows the income collected over the past twelve months. These two documents will not match because the T-12 includes months when units were vacant or tenants were in rent concessions, while the rent roll shows only the present situation.
When comparing the two, record the date of the rent roll and the end date of the T-12 period. Identify any units that were vacant during part of the T-12 period but are now leased, and note the difference in income. The lender will want to see that the project's income is improving or stable, and the reconciliation shows you understand the timing gap.
Distinguishing gross rent, collected income, net operating income, capital expenditures, debt service, and equity cash flow
A draw request that references project income should use the correct terms. Gross rent is the total of all signed leases before any deductions. Collected income is what actually arrived in the bank account. Net operating income (NOI) is collected income minus operating expenses. Capital expenditures (capex) are improvements that last more than one year, such as a new roof or HVAC system. Debt service is the sum of principal and interest payments due on the loan. Equity cash flow is the money left for the sponsor after all expenses and debt service are paid.
In a draw request, the lender cares most about whether collected income is sufficient to cover operating expenses and the interest reserve. If the project is still in lease-up, the lender may require that property income be applied to interest first, with the reserve covering any shortfall. [2]
Evidence checklist to include with the draw request
The following checklist covers the documents a sponsor should prepare and submit with each draw request. This is a suggested way to organize information, not a mandatory lender process.
- Draw reconciliation worksheet showing budget line items, reported completion percentages, requested amounts, and retainage.
- Signed inspection report dated within the lender's required window, with the inspector's findings on compliance and progress.
- Lien waivers from the general contractor and all subcontractors and suppliers who performed work during the current draw period. [1] The OCC's handbook notes that the construction draw request should include waivers from the project's subcontractors and suppliers indicating that payment has been received for the work completed. [1]
- Updated title policy or a preliminary title report showing no new mechanics liens. [1]
- Updated financial statements for the sponsor and guarantors, if the loan agreement requires periodic updates. [1]
- Updated credit report for the sponsor and guarantors, if required. [1]
- Confirmation that the borrower's minimum equity requirement is still in place. [1]
Asking the actual lender about specific draw requirements
Every lender has its own draw package format, inspection frequency, and retainage policy. The sponsor should ask the lender directly what documents are required, how often inspections must occur, and whether the lender uses its own inspector or accepts a third-party report. The OCC's handbook describes that banks typically require architect or engineering inspection reports with each draw to verify that work is done according to specification. [1] But the specific requirements should be confirmed with the actual lender.
What happens if the draw request and the inspection report do not match?
The lender will likely hold the draw until the discrepancy is resolved. The sponsor should identify the reason for the difference—for example, a line item was invoiced but not yet installed—and provide a written explanation with supporting documents.
Can the sponsor use loan funds to pay for work that is not yet inspected?
Generally no. The OCC's handbook states that funds should not be advanced unless the funds are to be used solely for the project being financed and as stipulated in the draw request and consistent with the loan agreement. [1] The lender will release funds only for work that has been inspected and verified.
Run the numbers on your deal
See how loan-to-cost and value at completion size a construction loan, how much equity is left to fund, and an estimated interest reserve.
Talk through your financing
Working on a real property? Send us the deal and a financing advisor will review it and get back to you. It costs nothing to ask and does not commit you to anything.
Requests are reviewed by Wraith Real Estate, a commercial real estate debt advisor (not a lender).