When you finance a ground-up development, lenders need to see exactly how much of the total project cost is the land and how much is everything else. A combined figure hides the risk profile of each stage.

Build a two-part sources and uses table

A sources and uses table is the single workpaper that answers most lender questions about land versus construction. Prepare one table with two sections.

Sources column. List every funding source: your equity, the construction loan, any mezzanine debt or preferred equity. Show the land contribution separately from cash equity. If you already own the land free and clear, record its contributed value at the lower of cost or current appraised value. [2] notes that a construction loan typically covers only part of the total cost, and the sponsor's equity covers the rest.

Uses column. Split uses into land, hard costs, soft costs and financing costs. Hard costs include materials, labor and contractor fees. Soft costs include architecture, engineering, legal, permits, marketing and leasing commissions. Financing costs include loan fees, interest during construction and the interest reserve. [1] includes a question for examiners about whether project cost estimates include land and construction costs, off-site improvement expenses, cost of legal services, loan interest, supervisory fees and insurance expenses.

Suggested way to prepare the information. Create the table in a spreadsheet. Label each line item. For land, note whether the amount is the original purchase price or a contributed value. For each hard and soft cost line, note whether the amount is from a signed contract or an estimate. This table becomes the basis for every lender conversation.

Understand why lenders separate land from construction

Record the stage of your project. If you are buying raw land with no immediate development plan, [1] notes that such loans are among the riskiest types of CRE loans and should require considerable equity. If you are buying land with a signed construction contract and permits in hand, the lender may view the combined acquisition-and-development as a single construction loan. Ask your lender which LTV limit applies to each stage of your project.

Identify the equity contribution from land

If you contribute land you already own, the lender will treat its value as part of your equity. [2] states that the sponsor's equity covers the part of the total cost not covered by the loan. The lender will order an appraisal of the land to confirm its current market value. The contributed value should be the lower of your original cost or that appraised value.

Compare cost and appraised value. If the land has appreciated since you bought it, the lender may accept the higher appraised value as your equity contribution, but only if the appraisal supports it. If the land has depreciated, the lender will use the lower appraised value, and you may need to add cash equity to meet the required loan-to-cost ratio. [1] says prudent policies typically establish loan limits as a maximum percentage of cost (loan-to-cost) as well as market value (loan-to-value) to ensure the borrower contributes sufficient equity.

Prepare a line-item construction budget

A single total number for construction is not enough. [1] includes a question for examiners about whether the bank requires a line-item budget or cost breakdown for each construction stage. Prepare a budget that lists each trade or phase: site work, foundation, framing, roofing, mechanical, electrical, plumbing, interior finishes, landscaping. Include the amount and source of the builder's or owner's equity contribution. [1] also includes a question for examiners about whether budgets include a contingency allowance for costs not included in the agreement with the contractor.

Suggested way to prepare the information. Use the same spreadsheet as your sources and uses table. Add a separate tab for the line-item budget. For each line, show the contract amount, the amount already paid, the amount remaining and the retainage held back. [2] explains that a share of each payment to the contractor is commonly held back as retainage and released as the work is substantially complete.

Include the interest reserve as a separate line

Interest during construction is a real cost that affects how much loan proceeds you need. [2] says the budget usually includes an interest reserve funded from loan proceeds, so interest during construction is paid from the loan rather than from the sponsor's own cash. [1] includes a question for examiners about whether project cost estimates include loan interest.

Calculate the interest reserve. Estimate the average outstanding loan balance during construction, multiply by the expected interest rate and multiply by the expected construction period in years. Add that amount to the uses column of your sources and uses table. If the interest reserve runs short, [2] notes the sponsor is typically required to fund the difference.

Ask the actual lender about guaranties and overruns

[1] warns that it is risky for a bank to extend unsecured working capital loans to fund a developer's equity investment or to cover cost overruns, as overruns may indicate an undercapitalized project or an inexperienced developer. [2] lists typical guaranties: a completion guaranty that the project will be finished lien-free and that cost overruns will be paid, and often a carry guaranty covering interest, taxes, insurance and other operating costs until the property meets agreed income or debt service coverage tests.

Suggested way to prepare the information. Before you submit the loan request, ask your lender whether it requires a completion guaranty, a carry guaranty or a repayment guaranty. Record the lender's answer in your deal file. If the lender requires a completion guaranty, confirm whether the guaranty covers only hard cost overruns or also soft cost overruns and interest reserve shortfalls.

Does the land need to be fully paid off before I apply for a construction loan?

Not always. Many lenders will allow you to include the land acquisition in the same loan as the construction, as long as the combined loan-to-cost and loan-to-value limits are met. [1] notes that acquisition and development loans are often extended together. If you already own the land, the lender will treat its contributed value as part of your equity. Ask your lender whether it will finance the land acquisition as part of the construction loan or whether it requires the land to be free and clear.

How do I prove the land value for the equity contribution?

The lender will order an appraisal of the land. You can also provide a copy of the purchase agreement or the deed showing the price you paid. If the land has appreciated, the appraised value will be used. If the land has depreciated, the lender will use the lower of cost or appraised value. [1] says the bank may use the higher appropriate LTV ratio when actual construction begins, but the land value itself is based on the appraisal.

What happens if the construction budget runs over?

The completion guaranty typically requires you to pay for cost overruns. [2] states that a completion guaranty covers that the project will be finished lien-free and that cost overruns will be paid. [1] warns that banks view overruns as a sign of an undercapitalized project or an inexperienced developer. Your budget should include a contingency allowance. If overruns occur, you will need to contribute additional equity or negotiate with the lender.

Run the numbers on your deal

See how loan-to-cost and value at completion size a construction loan, how much equity is left to fund, and an estimated interest reserve.

Open the construction calculator

Talk through your financing

Working on a real property? Send us the deal and a financing advisor will review it and get back to you. It costs nothing to ask and does not commit you to anything.

Contact us