Reconciling approved change orders with a revised project budget
A practical guide for commercial real estate sponsors on tracking change orders, updating the construction budget, and presenting a clear reconciliation to lenders during the financing process.
A practical guide for commercial real estate sponsors on tracking change orders, updating the construction budget, and presenting a clear reconciliation to lenders during the financing process.
Why change order reconciliation matters to your lender
When a construction project generates change orders, the lender needs to see those changes reflected in an updated budget. Bank supervisory guidance states that a significant number of change orders could indicate poor planning or project design, or problems in construction, and should be tracked and reflected in the project's budget [1]. This is not a rule that applies only to regulated banks, but it reflects how lenders generally evaluate project management discipline.
Your lender reviews change orders to understand whether the project is still on track. The construction budget, along with the project pro forma, is one of the most critical elements in determining project feasibility [1]. When you present a reconciliation, you are showing the lender that you are in control of costs and that the project remains viable.
What a change order reconciliation includes
A change order reconciliation is a document that shows every approved change order, its impact on the budget, and the updated total project cost. It is not the same as the original budget. It is a living document that you update as the project proceeds.
To prepare a reconciliation, you will need: - The original line-item construction budget showing hard costs and soft costs separately [1] - A log of every approved change order, including the date, description, amount, and approval signature - The revised budget that incorporates each change order into the appropriate line item - A summary that shows the original budget total, total change orders, and the revised total
A suggested way to organize this information is to create a simple spreadsheet with columns for the original budget line item, the change order reference, the change amount, and the revised line item total. This format helps the lender see exactly where costs have shifted.
Tracking change orders against the contingency account
When you approve a change order, you should first record whether it will be funded from the contingency account or from another source. If the change order exceeds the remaining contingency, the lender will want to know how you plan to cover the gap. The OCC guidance notes that developers typically give the bank a detailed line-item budget that should be reviewed by a qualified individual to assess the appropriateness and reasonableness of the budget [1]. Your reconciliation should identify whether the change order is within the contingency or requires additional equity or a loan increase.
How to present the reconciliation to your lender
Changes in construction plans should be reviewed by competent staff or a construction consulting firm and approved and documented by the bank and take-out lender, if any [1]. When you submit a reconciliation, include:
- A cover summary that states the original budget total, total approved change orders to date, and the revised budget total
- The change order log with dates, descriptions, and amounts
- The revised line-item budget showing where each change order was applied
- A note on the remaining contingency, if any
This is not a mandatory lender process, but it is a practical way to prepare information that lenders typically expect. The construction loan agreement should include a detailed budget and should identify all costs funded by the construction loan [1]. Your reconciliation should be consistent with that agreement.
What lenders look for in the reconciliation
Lenders review change order reconciliations to assess several things:
- Whether the change orders are reasonable and necessary for the project
- Whether the budget remains adequate to complete the project
- Whether the sponsor has sufficient financial capacity to cover any shortfall
The OCC guidance states that analysis of the borrower's financial condition should include a determination of whether the borrower has sufficient financial capacity for project completion [1]. If your reconciliation shows that change orders have consumed most or all of the contingency, the lender may ask for evidence that you can fund any further overruns.
Lenders also look for patterns. A significant number of change orders could indicate poor planning or project design, or problems in construction [1]. If you have many small change orders, you may want to explain why they arose and how you are managing the process.
Reconciling the budget with the pro forma
Changes in construction plans can affect the project's expected net operating income. The OCC guidance notes that regardless of the cost to construct a property, the value of an income-producing property depends to a great degree on the expected NOI [1]. Construction costs that closely approach or exceed the expected value of the project's income generally indicate that a project is not feasible [1].
When you update your budget for change orders, you should also update your pro forma to reflect any changes in the project's scope or completion date. The OCC guidance states that when key underlying assumptions change, the borrower should provide revised projections to the bank that reflect current conditions [1]. Your reconciliation should include a note on whether the change orders affect the project's expected NOI or stabilized value.
Preparing a change order reconciliation workpaper
Here is a concrete document you can prepare. Create a workpaper with these sections:
Section 1: Original budget summary - Total hard costs - Total soft costs - Contingency amount - Total project cost
Section 2: Change order log For each change order, record: - Change order number - Date approved - Description of the change - Amount - Whether funded from contingency, equity, or loan - Approval signature
Section 3: Revised budget Show each original line item, the change order reference, the change amount, and the revised line item total. Calculate the new total project cost.
Section 4: Remaining contingency Show the original contingency amount, total change orders drawn from contingency, and the remaining balance.
Section 5: Impact on pro forma Note whether the change orders affect the project's scope, completion date, or expected NOI. If so, attach a revised pro forma.
This workpaper is a suggested way to organize information. It is not a substitute for the lender's own review. The lender will still conduct its own analysis of the project, as the OCC guidance recommends [1].
How do I know if a change order should come from contingency or from additional equity?
Ask the actual lender how they prefer to handle change orders that exceed the contingency. Some lenders expect the sponsor to fund those costs from equity. Others may allow a loan increase if the project still meets loan-to-cost and loan-to-value tests. The OCC guidance notes that the budget typically includes a contingency account to fund unanticipated cost overruns [1], but it does not prescribe what happens when that account is exhausted.
Should I include change orders that have not been approved yet?
No. Only include approved change orders in your reconciliation. The OCC guidance states that changes in construction plans should be reviewed and approved and documented by the bank and take-out lender, if any [1]. Pending change orders should be tracked separately and presented to the lender for approval before they are included in the budget.
Does a change order always require a revised pro forma?
Not always, but you should consider whether the change order affects the project's expected income or completion date. The OCC guidance states that when key underlying assumptions change, the borrower should provide revised projections to the bank that reflect current conditions [1]. If the change order is minor and does not affect the project's scope or timeline, a simple note in the reconciliation may be sufficient.
This guide is for educational purposes and does not constitute a commitment to lend. If you have a project in mind, you can share the property, business plan, amount, and timing through our website to begin a preliminary discussion.*
Run the numbers on your deal
See how loan-to-cost and value at completion size a construction loan, how much equity is left to fund, and an estimated interest reserve.
Talk through your financing
Working on a real property? Send us the deal and a financing advisor will review it and get back to you. It costs nothing to ask and does not commit you to anything.
Requests are reviewed by Wraith Real Estate, a commercial real estate debt advisor (not a lender).