Documenting permits that remain outstanding in a construction financing package
A practical guide to preparing a permit evidence workpaper that shows lenders what permits are still pending, which have been issued, and how outstanding permits affect the budget, schedule, and contingency analysis in a commercial construction loan request.
A practical guide to preparing a permit evidence workpaper that shows lenders what permits are still pending, which have been issued, and how outstanding permits affect the budget, schedule, and contingency analysis in a commercial construction loan request.
When a commercial construction project has permits that are still pending at the time of a loan request, lenders need to understand what is outstanding, why it matters to the budget and schedule, and how the sponsor plans to manage the risk. This guide walks through the specific documents and analysis a sponsor can prepare to address outstanding permits clearly, without guessing what any particular lender will require.
What lenders typically review about permits
Lenders underwrite a construction loan against an approved budget and a schedule, and they advance money in draws as work is completed and inspected [2]. The OCC's supervisory guidance notes that banks are expected to maintain sound credit administration and monitoring programs, including timely monitoring of construction progress and evaluating work performed against project design and budget [1]. Permits are part of that evaluation because they affect whether construction can proceed on schedule and within the approved budget.
A suggested way to prepare information is to create a single workpaper that lists every permit the project requires, its status, the date applied, the expected decision date, and the contingency or budget line item that covers any delay or re-application cost. This workpaper is not a lender form; it is a record you prepare to support the financing discussion.
Creating a permit status workpaper
The workpaper should include the following columns for each permit:
- Permit name and issuing authority
- Date applied
- Current status (issued, pending, revised, denied)
- Expected decision date or actual issuance date
- Budget line item or contingency that covers permit fees and any delay costs
- Impact on construction schedule if permit is delayed beyond the expected decision date
- Notes on any conditions attached to issued permits
Record the source of each status entry, such as a screenshot from the municipal portal, a letter from the permitting office, or an email from the project architect. Lenders may ask to see the original documentation, so keep copies organized by permit.
How outstanding permits affect the budget discussion
A lender sizes the loan against the total cost of the project and against its value on completion or stabilization [2]. If permits are outstanding, the budget should include a contingency allowance for costs not included in the agreement with the contractor [1]. The OCC guidance lists project cost estimates as including land and construction costs, off-site improvement expenses, cost of legal services, loan interest, supervisory fees, and insurance expenses [1]. Permit fees and potential delay costs fit within these categories.
A practical step is to compare the total permit fees and estimated delay costs against the contingency line item in the budget. If the contingency is too small to cover a realistic permit delay, identify that gap in the workpaper. This is not a mandatory lender process; it is a suggested way to prepare information so you can discuss the risk with the lender.
How outstanding permits affect the schedule discussion
Lenders typically require a construction completion schedule [1]. If permits are outstanding, the schedule should show which permit is needed before which construction phase can begin. For example, a foundation permit must be issued before excavation can start, and a framing permit may be needed before vertical construction.
Identify the critical path permits and note in the workpaper whether the schedule has a buffer or float that can absorb a delay. If the schedule assumes permits will be issued on the expected decision date, and that date has already passed, the workpaper should flag that assumption as uncertain.
Distinguishing issued permits from pending ones
A permit status workpaper should distinguish between permits that have been issued and those that are still pending. An issued permit is a completed event; a pending permit is a future uncertainty. Do not treat a pending permit as if it were issued simply because the application was filed.
If a permit has conditions attached, note those conditions in the workpaper. For example, a permit may require a bond, a traffic study, or a sign-off from another agency before construction can begin. Those conditions are part of the permit status, not separate from it.
How to present the workpaper to a lender
A suggested way to present the workpaper is as a single-page table attached to the budget and schedule exhibits in the loan request. Include a short narrative that explains:
- Which permits are still pending
- Why each one is needed and what phase of construction it affects
- What the contingency covers if a permit is delayed or denied
- What steps the sponsor has taken to expedite or resolve outstanding permits
This narrative is not a guarantee of permit clearance or liability protection; it is a record of the sponsor's preparation. The OCC guidance notes that examiners should be aware of front loading, where a builder deliberately overstates the cost of work to be completed in early stages [1]. A clear permit workpaper helps demonstrate that the sponsor is not front-loading the budget or schedule.
What to do if a permit is denied or delayed
If a permit has been denied or delayed significantly, the workpaper should note the reason and the plan to resolve it. This may include re-applying with revised plans, appealing the decision, or obtaining a variance. The budget should reflect the cost of re-application, revised plans, and any legal or consulting fees.
A lender may ask about the sponsor's experience with the property type and the market [2]. If the sponsor has handled permit issues on similar projects before, that experience can be noted in the workpaper. If the sponsor has not, the workpaper should show that a qualified architect, engineer, or permit expediter is engaged to manage the process.
Suggested checklist for permit documentation
Record the following for each permit:
- Permit name and issuing authority
- Date applied
- Current status
- Expected decision date or actual issuance date
- Budget line item or contingency that covers permit fees and delay costs
- Impact on construction schedule if permit is delayed
- Conditions attached to issued permits
- Source documentation for each status entry
Compare the total permit fees and estimated delay costs against the contingency line item. Identify any gap where the contingency is too small to cover a realistic delay.
Flag any permit that is on the critical path and note whether the schedule has a buffer or float that can absorb a delay.
If a permit has been denied or delayed, record the reason and the plan to resolve it, including estimated costs and timeline.
FAQs
How do I know which permits my project needs?
Ask the project architect, engineer, or general contractor to provide a complete list of permits required by the local jurisdiction. Common permits include building, electrical, plumbing, mechanical, foundation, framing, and occupancy permits. Some projects may also require environmental, zoning, or historic preservation approvals.
Should I include permit fees in the hard costs or soft costs of the budget?
Permit fees are typically classified as soft costs because they are not direct construction labor or materials. However, some lenders may ask to see them listed as a separate line item. The important step is to include them somewhere in the budget and to show that the contingency covers potential delay costs, not just the fees themselves.
What if a permit is still pending when the lender wants to close the loan?
Some lenders may require that all material permits be issued before closing, while others may allow a condition in the loan agreement that the borrower must obtain the permit by a certain date or before a certain draw. Ask the actual lender what its policy is for pending permits at closing. The workpaper helps show that you have identified the risk and planned for it.
It prepares the loan request with the sponsor, including the budget, the schedule, and the pro forma, and takes it to lenders suited to the project's size, market, and structure [2]. Submission is a preliminary request, not an engagement or lender submission. To start the conversation, share the property, business plan, amount, and timing through the website.
Run the numbers on your deal
See how loan-to-cost and value at completion size a construction loan, how much equity is left to fund, and an estimated interest reserve.
Talk through your financing
Working on a real property? Send us the deal and a financing advisor will review it and get back to you. It costs nothing to ask and does not commit you to anything.
Requests are reviewed by Wraith Real Estate, a commercial real estate debt advisor (not a lender).