Documenting interest carry separately from hard construction costs
A construction budget that lumps interest carry into hard costs or soft cost overhead invites lender concern and may delay draws. This guide explains how to separate interest reserve documentation, reconcile it with the draw schedule, and prepare a simple interest carry worksheet that matches what a lender's construction consultant will review.
A construction budget that lumps interest carry into hard costs or soft cost overhead invites lender concern and may delay draws. This guide explains how to separate interest reserve documentation, reconcile it with the draw schedule, and prepare a simple interest carry worksheet that matches what a lender's construction consultant will review.
Interest carry is a soft cost, not a hard cost
Hard costs include on- or off-site improvements, building construction, general conditions, general contractor's fees, bonding and contractor insurance [1]. Soft costs include interest and other development costs such as fees and predevelopment expenses [1]. An interest reserve is a budget line item that covers loan interest during construction and lease-up [1]. By separating the interest carry from hard costs in your budget schedule, you give the lender a clear view of how much of the loan proceeds will pay interest versus build physical improvements.
Build a simple interest carry worksheet
A suggested way to prepare this information is to create a worksheet with three columns: draw month, projected outstanding principal, and interest cost for that period. For each month in the construction and lease-up schedule, estimate the cumulative amount drawn, apply the expected interest rate (or a range if the loan is floating), and calculate the monthly interest. Sum the column to get the total interest reserve needed. This worksheet is not a lender requirement, but it helps you compare your interest carry estimate with the contingency and total soft cost line items in the budget.
Match the interest reserve to the draw schedule
Interest reserves should be used in a manner consistent with safe and sound banking practices, and an appropriate reserve provides sufficient funds to pay interest through the project's anticipated completion and lease-up, sale, or occupancy [1]. Your worksheet should reflect the timing of expected disbursements and pay downs [1]. If the lender funds draws monthly but the contractor's payment cycle is biweekly, your interest carry calculation should align with the draw dates, not the contractor's invoices. Record the assumed draw dates and amounts in the worksheet so the lender can see the logic.
Distinguish interest carry from other soft costs
Soft costs include interest and other development costs such as fees and predevelopment expenses [1]. Interest or preferred returns payable to equity partners or subordinated debt holders should not be included in the construction budget [1]. If your project includes a developer fee, leasing commissions, or management fees, list those separately in the soft cost section. Do not bury interest carry inside a general "soft cost contingency." Identify the interest reserve as a distinct line item with its own subtotal.
Prepare for lease-up interest coverage
During the lease-up period, any cash flow from the project is ordinarily applied to interest first, with the reserve covering any shortfall [1]. Your worksheet should include a lease-up phase with projected rental income and the resulting interest shortfall each month. If the reserve runs short, the sponsor is typically required to fund the difference [2]. Ask the actual lender whether they expect the interest reserve to cover the full lease-up period or only until the property reaches a certain occupancy or debt service coverage ratio.
Reconcile the interest reserve with the total budget
The construction budget, along with the project pro forma, is one of the most critical elements in determining project feasibility [1]. A contingency account typically funds unanticipated cost overruns such as an unexpected increase in material costs or a buyer-mandated redesign [1]. The interest reserve should be sized separately from the contingency. If the interest reserve is depleted, that may indicate an underperforming construction process [1]. Compare your interest carry worksheet against the total soft cost line and the contingency to ensure you are not double-counting or underestimating.
Evidence checklist for your file
Before you submit a budget to a lender, gather these items:
- A line-item budget that separates hard costs, soft costs, and the interest reserve as a distinct soft cost line [1].
- An interest carry worksheet showing monthly projected draws, outstanding principal, and interest cost for the construction and lease-up period.
- The construction completion schedule and lease-up timeline used to calculate the interest carry [1].
- If the interest reserve will be funded by the borrower into a separate escrow account, evidence of the escrow arrangement [1].
- If the interest reserve is funded from loan proceeds, a note in the budget showing the reserve as a soft cost line item [1].
- If the project will generate cash flow during lease-up, a pro forma showing how that cash flow is applied to interest first [1].
- A statement of the sponsor's equity contribution and how it relates to the interest reserve, particularly if the sponsor intends to pay interest from its own funds [1].
Frequently asked questions
Does the interest reserve count toward loan-to-cost?
Yes. The interest reserve is a soft cost and is included in the total project cost when calculating loan-to-cost [2]. Lenders typically test the loan amount against both total cost and the appraised value on completion or stabilization [2].
Can the interest reserve be funded from the contingency?
No. The contingency is for unanticipated cost overruns such as material cost increases or redesigns [1]. The interest reserve should be a separate line item sized to the expected interest carry. Using the contingency for interest may indicate an underperforming construction process [1].
What happens if the interest reserve runs out before lease-up is complete?
The sponsor is typically required to fund the difference [2]. Lenders may also require a carry guaranty covering interest, taxes, insurance and other operating costs until the property meets agreed income or debt service coverage tests [2].
Submission of a loan request is a preliminary step, not an engagement or lender submission.
Run the numbers on your deal
See how loan-to-cost and value at completion size a construction loan, how much equity is left to fund, and an estimated interest reserve.
Talk through your financing
Working on a real property? Send us the deal and a financing advisor will review it and get back to you. It costs nothing to ask and does not commit you to anything.
Requests are reviewed by Wraith Real Estate, a commercial real estate debt advisor (not a lender).